This complex project was the construction of a new emergency power facility connecting to the hospital’s existing central plant. It featured the installation of two 2000kW generators with associated equipment and fuel tanks, as well as final project commissioning.
The work centralized OSHPD campus emergency power and created vital infrastructure to support future expansions. This project was performed on an occupied OSHPD campus, under a public work design-build contract.